Assignment please See the attached file
Consider a project that consists of activities named A, B, ..., M. The following table gives the
predecessors and the duration in days of each of these activities.
Activity Predecessors Duration
A 5
B A 2
C B 2
D A 2
E C 10
F D,C 6
G C 13
H F,E,G 15
I A 2
J E 3
K F,E,I 6
L C,D 2
M D,J,I 3
1. Use the CPM method to find the critical path in this project. Show the details of the
calculation using the graphical representation seen during the lectures.
2. For each activity, give the impact on the completion date of the project if this activity
is delayed by 7 days. Justify your answers. Present the results in a table as follows:
Activity Impact, if delayed by 7 days Justification
A
B
C
D
E
F
G
H
I
J
K
L
M
1
Các kĩ năng yêu cầu
Những bài dự thi tốt nhất dự cuộc thi này
-
engselgendy Egypt
Bảng thông báo công khai
Làm thế nào để bắt đầu với cuộc thi
-
Đăng cuộc thi của bạn Nhanh chóng và dễ dàng
-
Nhận được vô số Bài dự thi Từ khắp nơi trên thế giới
-
Trao giải cho bài thi xuất sắc nhất Download File - Đơn giản!